Suppose that a material has a lead time of three days and that the average usage of

Question:

Suppose that a material has a lead time of three days and that the average usage of the material is 12 units per day. What is the reorder point? If the maximum usage is 15 units per day, what is the safety stock?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question