For Tracey Company, units to be produced are 5,000 in quarter 1 and 6,000 in quarter 2.

Question:

For Tracey Company, units to be produced are 5,000 in quarter 1 and 6,000 in quarter 2. It takes 1.6 hours to make a finished unit, and the expected hourly wage rate is $15. Prepare a direct labour budget by quarters for the six months ending June 30, 2022.