15 The activities required to design a prototype of an experimental machine are listed in the following

Question:

15 The activities required to design a prototype of an experimental machine are listed in the following table, along with their immediate predecessors and estimated durations.

ACTIVITY IMMEDIATE PREDECESSORS TIME

(days)

A — 5 B — 4 C A 2 D A 1 E B 5 F B 7 G C, E 9 H D, F 6

(a) Develop a project network for this problem.

(b) Determine the EST, EFT, LST, LFT, and slack for each activity. Also determine the total project completion time and the critical path(s).

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: