15 The activities required to design a prototype of an experimental machine are listed in the following
Question:
15 The activities required to design a prototype of an experimental machine are listed in the following table, along with their immediate predecessors and estimated durations.
ACTIVITY IMMEDIATE PREDECESSORS TIME
(days)
A — 5 B — 4 C A 2 D A 1 E B 5 F B 7 G C, E 9 H D, F 6
(a) Develop a project network for this problem.
(b) Determine the EST, EFT, LST, LFT, and slack for each activity. Also determine the total project completion time and the critical path(s).