14 The Pickett Marketing Firm is developing a new Web-based media campaign for a client. The following

Question:

14 The Pickett Marketing Firm is developing a new Web-based media campaign for a client. The following table describes the relationships between the activities that need to be completed.

ACTIVITY IMMEDIATE PREDECESSORS TIME

(days)

A — 4 B A 6 C B 12 D B 11 E D 9 F D 8 G D 10 H C 5 I C 7 J E, F, G 4 K H, I 9

(a) Develop a project network for this problem.

(b) Determine the EST, EFT, LST, LFT, and slack for each activity. Also determine the total project completion time and the critical path(s).