28 Susan Rogers project (see Problem 27) has progressed over the past several weeks, and it is...
Question:
28 Susan Roger’s project (see Problem 27) has progressed over the past several weeks, and it is now the end of week 8. Susan would like to know the current status of the project with regard to schedule and budget by developing an appropriate table. Assume that all activities follow their earliest time schedules.
The relevant data are shown in the following table.
ACTIVITY PERCENTAGE COMPLETED ACTUAL COST A 100 $1,900 B 100 $5,300 C 100 $6,150 D 40 $1,800 E 60 $1,755 F 0 $ 0
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Managerial Decision Modeling With Spreadsheets
ISBN: 9781292024196
3rd Edition
Authors: Barry Render
Question Posted: