29 General Foundrys project crashing data are shown in Table 10 . Crash this project by hand...

Question:

29 General Foundry’s project crashing data are shown in Table 10 . Crash this project by hand to 10 weeks. What are the final times for each activity after crashing, and what is the total cost associated with reducing the duration of this project from 15 to 10 weeks?