A risk assessment was completed three months ago and has recently been approved. What should be done
Question:
A risk assessment was completed three months ago and has recently been approved. What should be done first to implement a mitigation plan?
A. Verify risk elements
B. Purchase countermeasures
C. Redo risk assessment
D. Redo the CBA