Johnson accepted an offer from another company, and Isabel has inherited the project to manage to completion.

Question:

Johnson accepted an offer from another company, and Isabel has inherited the project to manage to completion. Johnson cannot be reached, so Isabel is forced to search project documents to get what she needs. She found the contracts to be very helpful, but Isabel wants to make sure she has a full comprehension of the expectations of the sponsor. What two documents would be most useful?

A. The stakeholder register and the communications management plan.

B. The WBS and the project charter.

C. The communication management plan and the scope statement.

D. The communication plan and the stakeholder management strategy.