Margaret is gathering information from the last month of project activity as she prepares to meet with

Question:

Margaret is gathering information from the last month of project activity as she prepares to meet with key stakeholders, make sure they are getting the data they need, and respond to any issues.

Margaret is looking for all supporting data related to a recent request to modify the shipping specifications for vital parts. She recalls that this topic of shipping requirements was a very big concern for one of the customers, but she cannot remember who that person was. What two items will be key inputs to Margaret in this process?

A. Requirements documentation and Work performance information.

B. Issue log and Stakeholder engagement plan.

C. Change log and Responsibility assignment matrix.

D. Change log and the Work breakdown structure.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: