The team is getting slightly behind on the project schedule, so Francine has moved team members Joseph

Question:

The team is getting slightly behind on the project schedule, so Francine has moved team members Joseph and Sally from their prior assignments to new tasks. Rick is thrilled because he had been working nights and weekends in an effort to complete the task -

now, he has help! What process is being described, and what tool has Francine used?

A. Develop Schedule and the tool of Resource Leveling.

B. Estimate Activity Durations and the tool of Crashing.

C. Develop Schedule and the schedule compression tool of Crashing.

D. Control Schedule and the tool of Resource Optimization.