The team is getting slightly behind on the project schedule, so Francine has moved team members Joseph
Question:
The team is getting slightly behind on the project schedule, so Francine has moved team members Joseph and Sally from their prior assignments to new tasks. Rick is thrilled because he had been working nights and weekends in an effort to complete the task -
now, he has help! What process is being described, and what tool has Francine used?
A. Develop Schedule and the tool of Resource Leveling.
B. Estimate Activity Durations and the tool of Crashing.
C. Develop Schedule and the schedule compression tool of Crashing.
D. Control Schedule and the tool of Resource Optimization.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
The PMP Exam: How To Pass On Your First Try (Test Prep Series)
ISBN: 9781732055711
6th Edition
Authors: Andy Crowe
Question Posted: