Theresa took over for another PM after about half of the project was completed. She is looking
Question:
Theresa took over for another PM after about half of the project was completed. She is looking for guidance for how she might reward team members for excellent performance. What document is the best source for finding that specific information?
A. Staffing management plan.
B. Resource management plan.
C. Human resource plan.
D. Reward guidelines.