Which of the following is the best description of the project plan? A. A formal, approved document

Question:

Which of the following is the best description of the project plan?

A. A formal, approved document that consolidates all subsidiary management plans and baselines from planning processes.

B. The formal, approved document that integrates planning processes and tells how the project measurement baseline will be defined.

C. The formal, approved document that contains the work breakdown structure, schedule management plan, budget, contracts, cost management plan, and quality management plan.

D. The document that outlines all of the work to be performed on a project and how change requests will be managed.