Which of these statements about a work breakdown structure is not accurate?
A. Once the scope baseline is established, the WBS should represent all the official scope of the project.
B. The number of levels in a WBS will vary.
C. The goal with decomposing the WBS is to keep going until you don’t know enough information to continue decomposing or you’ve reached the work package level.
D. The WBS results in many work packages that all have a single schedule activity associated with them.