You are the project manager for a project, and the Customer just asked for a cost estimate
Question:
You are the project manager for a project, and the Customer just asked for a cost estimate for a group of tasks the team will perform.
What type of estimate would you prefer that the Customer request from you?
A. Control.
B. Definitive.
C. ROM.
D. Parenthetical.