If BAC = $20,000 and the project is 40% complete, then the earned value is: a. $5,000

Question:

If BAC = $20,000 and the project is 40% complete, then the earned value is:

a. $5,000

b. $8,000

c. $20,000

d. Cannot be determined

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: