If CPI = 1.1 and SPI = 0.95, then the trend for the project is: a. Running
Question:
If CPI = 1.1 and SPI = 0.95, then the trend for the project is:
a. Running over budget but ahead of schedule
b. Running over budget but behind schedule
c. Running under budget but ahead of schedule
d. Running under budget but behind schedule