Select one and only one of the listed acronyms to answer each question. PV EV AC BAC
Question:
Select one and only one of the listed acronyms to answer each question.
PV EV AC BAC SV CV EAC ETC
a. What is the revised estimate for the final cost at the completion of the project?
b. How much money was expended thus far?
c. How much physical work was actually accomplished thus far? _____
d. How much money was originally budgeted?
e. From where we are today, how much money is needed to complete the work?
f. By how much have we deviated from the schedule baseline, favorably or unfavorably?
g. By how much have we deviated from the cost baseline, favorably or unfavorably?
h. What is the planned cost or value of the work accomplished thus far?