The major disadvantage of using bar charts to manage a project is that bar charts: a. Do

Question:

The major disadvantage of using bar charts to manage a project is that bar charts:

a. Do not show dependencies between activities

b. Are ineffective for projects under one year in length

c. Are ineffective for projects under $1 million in size

d. Do not identify start and end dates of a schedule