Which of the following stakeholder actions can lead to metric management failure? a. Mistrust among the stakeholders
Question:
Which of the following stakeholder actions can lead to metric management failure?
a. Mistrust among the stakeholders
b. Failing to understanding the metrics
c. Failing to agree on how to measure the metrics
d. All of the above