You are a project manager for Move It Now trucking company. Your company specializes in moving household
Question:
You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the standard deviation?
A. 22 B. 20 C. 2 D. 4