You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D department has agreed to release two resources to work on your project in order to meet the federal grant application date. This is an example of ___________________ .
A. Crashing B. Fast tracking C. Resource leveling D. Adjusting the resource calendar