You re working on a project in which the time to complete the project has been
Question:
You ’ re working on a project in which the time to complete the project has been heavily restricted and funds are short. You have one resource working on preparing six servers for use in a balanced web array. The servers will all look basically alike. What technique can you use to slim down some of the time required to perform this task in the project?
A. Fast tracking B. Crashing C. Reducing the number of servers D. Purchasing a server that runs a number of virtual machines simultaneously