You re working on a project that you and your team have estimated takes 15 business

Question:

You ’ re working on a project that you and your team have estimated takes 15 business days to complete. Your team does not work on Saturday, Sunday, or holidays. Given the work calendar shown here and a start date of Tuesday, November 1, what is the scheduled completion date for this task?image text in transcribed

A. 21 B. 15 C. 22 D. 23