Your project was just completed. Due to some unfortunate circumstances, the project was delayed, causing cost overruns

Question:

Your project was just completed. Due to some unfortunate circumstances, the project was delayed, causing cost overruns at the end of the project. This information might be useful on future projects in all of the following activities except for which one?

A. Cost estimating B. Allocating resources C. Product verification D. Activity estimating