Your task requires 4 miles of paving, and it will take 30 hours to complete a mile. On a past project similar to this one, it took 150 hours to complete. Which of the following is true regarding this estimate?
A. The total estimate for this task is 120 hours, which was derived using expert judgment.
B. The total estimate for this task is 120 hours, which was derived using parametric estimating.
C. The total estimate for this task is 150 hours, which was derived using analogous estimating.
D. The total estimate for this task is 150 hours, which was derived using expert judgment.