A project has been defined to contain the following list of activities along with their required times
Question:
A project has been defined to contain the following list of activities along with their required times for completion.
a. Draw a network diagram for the activities.
b. Calculate the earliest expected completion time.
c. Show the critical path.
d. What would happen if activity 6 were revised to take 6 weeks instead of 2 weeks?
Step by Step Answer:
Related Book For
Modern Systems Analysis And Design
ISBN: 9780132991308
7th Edition
Authors: Jeffrey A Hoffer, Joey George, Joseph S Valacich
Question Posted: