Question: Draw a network diagram for the tasks shown in Problem and Exercise 3-45. Highlight the critical path. Problem and Exercise 3-45. Assume that you have
Draw a network diagram for the tasks shown in Problem and Exercise 3-45. Highlight the critical path.
Problem and Exercise 3-45.
Assume that you have a project with seven activities labeled A–G (below). Derive the earliest completion time (or early finish—EF), latest completion time (or late finish—LF), and slack for each of the following tasks (begin at time = 0). Which tasks are on the critical path? Draw a Gantt chart for these tasks.

Preceding Expected Duration Event Critical EF LF Slack Path? Activity A 5 B A 3 A 4 D E , 4 1 G D, E, F 5
Step by Step Solution
3.46 Rating (172 Votes )
There are 3 Steps involved in it
ACTIVITY DURATION ES EF LS LF SLACK CRITICAL A 5 0 0 5 5 5 5 0 MIN LSB C 5 5 5 0 YES B ... View full answer