Question: Draw a network diagram for the tasks shown in Problem and Exercise 3-45. Highlight the critical path. Problem and Exercise 3-45. Assume that you have

Draw a network diagram for the tasks shown in Problem and Exercise 3-45. Highlight the critical path.


Problem and Exercise 3-45.

Assume that you have a project with seven activities labeled A–G (below). Derive the earliest completion time (or early finish—EF), latest completion time (or late finish—LF), and slack for each of the following tasks (begin at time = 0). Which tasks are on the critical path? Draw a Gantt chart for these tasks.

Preceding Expected Duration Event Critical EF LF Slack Path? Activity A 5 B A 3 A 4 D E В, С 4 1 G D, E, F 5

Preceding Expected Duration Event Critical EF LF Slack Path? Activity A 5 B A 3 A 4 D E , 4 1 G D, E, F 5

Step by Step Solution

3.46 Rating (172 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

ACTIVITY DURATION ES EF LS LF SLACK CRITICAL A 5 0 0 5 5 5 5 0 MIN LSB C 5 5 5 0 YES B ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Modern Systems Analysis And Design Questions!