Question: Draw a Gantt chart for the tasks shown in Problem and Exercise 3-47. Problem and Exercise 3-47. Assume you have a project with ten activities

Draw a Gantt chart for the tasks shown in Problem and Exercise 3-47.

 

Problem and Exercise 3-47.

Assume you have a project with ten activities labeled A–J, as shown. Derive the earliest completion time (or early finish—EF), latest completion time (or late finish—LF), and slack for each of the following tasks (begin at time = 0). Which tasks are on the critical path? Highlight the critical path on your network diagram.

Preceding Event Expected Duration Critical EF LF Slack Path? Activity A В A A D A E A, D 6 F С, Е G D, E H E 3 F, G H, I 45o7 o542 45

Preceding Event Expected Duration Critical EF LF Slack Path? Activity A A A D A E A, D 6 F , G D, E H E 3 F, G H, I 45o7 o542 45

Step by Step Solution

3.32 Rating (161 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To calculate the earliest completion time EF latest completion time LF and slack for each activity w... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Modern Systems Analysis And Design Questions!