Question

1 Approved Answer

Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest completion time (or early finish-EF), latest completion time (or late

Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest completion time (or early finish-EF), latest completion time (or late finish-LF), and slack for each of the following tasks (begin at time = 0). What tasks are on the critical path? Highlight the critical path on your network diagram.

Activity

Preceding Event

Expected Duration

EF

LF

Slack

Critical Path?

A

-

4

B

A

5

C

A

6

D

A

7

E

A, D

6

F

C, E

5

G

D, E

4

H

E

3

I

F, G

4

J

H, I

5

Explain what would happen if:

1. Task E is postponed by 3 days

2. Task G is postponed by 2 days


Step by Step Solution

3.39 Rating (146 Votes )

There are 3 Steps involved in it

Step: 1

Answer Below is the Network Diagram ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Derivatives Markets

Authors: Rober L. Macdonald

4th edition

321543084, 978-0321543080

More Books

Students also viewed these Mathematics questions