A project to build a new bridge seems to be going very well since the project is

Question:

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the fi rst two activities have been totally completed and the third activity is 60% complete. The planners were only expecting to be 50% through the third activity at this time.

The fi rst activity involves prepping the site for the bridge. It was expected that this would cost $1,420,000 and it was done for only $1,300,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,500,000 but was actually done for

$9,000,000. The third and fi nal activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,500,000. To date they have spent $5,000,000 on the superstructure.

Calculate the schedule variance, schedule performance index, and the cost index for the project to date. How is the project going?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations And Supply Management: The Core

ISBN: 9780073403335

2nd Edition

Authors: F. Robert Jacobs, Richard Chase

Question Posted: