Here is a CPM network with activity times in weeks: G(3) E(4) B(5) A(7) F(8) C(6) D(6)

Question:

Here is a CPM network with activity times in weeks:

G(3)

E(4)

B(5)

A(7)

F(8)

C(6)

D(6)

a. Determine the critical path.

b. How many weeks will the project take to complete?

c. Suppose F could be shortened by two weeks and B by one week. How would this affect the completion date?