Here is a CPM network with activity times in weeks:
G(3)
E(4)
B(5)
A(7)
F(8)
C(6)
D(6)
a. Determine the critical path.
b. How many weeks will the project take to complete?
c. Suppose F could be shortened by two weeks and B by one week. How would this affect the completion date?