Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) a. Draw the network. b. What
Question:
Schedule the following activities using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
a. Draw the network.
b. What is the critical path?
c. How many weeks will it take to complete the project?
d. Which activities have slack, and how much?
Step by Step Answer:
Related Book For
Operations And Supply Management: The Core
ISBN: 9780073403335
2nd Edition
Authors: F. Robert Jacobs, Richard Chase
Question Posted: