Bracket Manufacturing uses a Kanban system for a component. Daily demand is 1000 units. Each container has

Question:

Bracket Manufacturing uses a Kanban system for a component. Daily demand is 1000 units. Each container has a combined waiting and processing time of .85 days. If the container size is 70 and the alpha value (a) is 13%, how many kanban card sets should be authorized? What is the maximum authorized inventory?