The following AON chart was prepared at the beginning of an important software upgrade project. The duration, in days, follows the letter of each activity. What is the critical path? Which activities should be monitored most closely?
At the end of the first week, it was noted that activity A was completed in 2.5 days, but activity B required 4.5 days.
What impact does this have on the project? Are the same activities critical?