What is the tracking signal for the end of period 39 when actual demand is 800 units

Question:

What is the tracking signal for the end of period 39 when actual demand is 800 units and the forecast is 700 units in period 39. The algebraic sum of the forecast errors at the end of period 38 was -111 units. Assume that MAD is computed at the end of period 39 to be 2.11. What does this tracking signal mean?