An analyst has timed a metal-cutting task for 50 cycles. The average time per cycle was 10.40

Question:

An analyst has timed a metal-cutting task for 50 cycles. The average time per cycle was 10.40 minutes, and the standard deviation was 1.20 minutes for a worker with a performance rating of 125 percent. Assume an allowance of 16 percent of task time. Calculate the standard time for this task.