Five data entry operators work at the data processing department of the Birmingham Bank. Each day for
Question:
Five data entry operators work at the data processing department of the Birmingham Bank. Each day for 30 days, the number of defective records in a sample of 250 records typed by these operators has been noted, as follows:
SAMPLE NO.
NO.
DEFECTIVE SAMPLE NO.
NO.
DEFECTIVE SAMPLE NO.
NO.
DEFECTIVE 1 7 11 18 21 17 2 5 12 5 22 12 3 19 13 16 23 6 4 10 14 4 24 7 5 11 15 11 25 13 6 8 16 8 26 10 7 12 17 12 27 14 8 9 18 4 28 6 9 6 19 6 29 12 10 13 20 16 30 3
a) Establish 3s upper and lower control limits.
b) Why can the lower control limit not be a negative number?
c) The industry standards for the upper and lower control limits are 0.10 and 0.01, respectively. What does this imply about Birmingham Bank’s own standards?
Step by Step Answer:
Operations Management Sustainability And Supply Chain Management
ISBN: 9781292295039
13th Global Edition
Authors: Jay Heizer, Barry Render, Chuck Munson