Refer to Problem 10.13. a) If the allowance factor is 15%, what is the standard time for
Question:
Refer to Problem 10.13.
a) If the allowance factor is 15%, what is the standard time for this operation?
b) If the allowance factor is 18% and the performance rating is now 90%, what is the standard time for this operation? lop25