Sara James Bakery, described in Examples S1 and S2, has decided to increase its facilities by adding

Question:

Sara James Bakery, described in Examples S1 and S2, has decided to increase its facilities by adding one additional process line. The firm will have two process lines, each working 7 days a week, 3 shifts per day, 8 hours per shift, with effective capacity of 300,000 rolls. This addition, however, will reduce overall system efficiency to 85%. Compute the expected production with this new effective capacity.