Supervisor Kenneth Peterson wants to determine the percentage of time a machine in his area is idle.

Question:

Supervisor Kenneth Peterson wants to determine the percentage of time a machine in his area is idle. He decides to use work sampling, and his initial estimate is that the machine is idle 20%

of the time. How many observations should Peterson take to be 98%

confident that the results will be less than 5% from the true results? lop25