The following five overhaul jobs are waiting to be processed at Avianics Engine Repair Inc. These jobs

Question:

The following five overhaul jobs are waiting to be processed at Avianic’s Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days.

Assume that all jobs arrived on day 180; today’s date is 200.

JOB DUE DATE REMAINING TIME (DAYS)
103 214 10 205 223 7 309 217 11 412 219 5 517 217 15 Using the critical ratio scheduling rule, in what sequence would the jobs be processed? L 0 1 