The job that should be scheduled last when using Johnsons rule is the job with the: a)

Question:

The job that should be scheduled last when using Johnson’s rule is the job with the:

a) Largest total processing time on both machines.

b) Smallest total processing time on both machines.

c) Longest activity time if it lies with the first machine.

d) Longest activity time if it lies with the second machine.

e) Shortest activity time if it lies with the second machine.

Fantastic news! We've Found the answer you've been seeking!