The tasks shown in the following precedence diagram are to be assigned to workstations with the intent of minimizing idle time. Management has designed an output rate of 275 units per day. Assume 440 minutes are available per day.
a. Determine the appropriate cycle time.
b. What is the minimum number of stations possible?
c. Assign tasks using the “positional weight” rule: Assign tasks with highest following times
(including a task’s own time) first. Break ties using the greatest number of following tasks.
d. Compute efficiency