A company that manufactures roofing materials for houses has the following demand forecasts for the next 4

Question:

A company that manufactures roofing materials for houses has the following demand forecasts for the next 4 weeks.

Week 2 Material Forecast (in tons) 70 50 80 60


The company€™s available capacities for labor and machines and their production work standards are also given as follows:

Labor Machine Production Work Standard (in hours per ton) 6. 4 Weekly Available Capacity (in hours) 450 300


1. What is the capacity utilization for each resource for each of the next 4 weeks?

2. Do you anticipate capacity-related problems in any of the 4 weeks? What are your recommendations to address the problems?