A construction project has indirect costs totalling $40,000 per week Major activities in the project and their

Question:

A construction project has indirect costs totalling $40,000 per week Major activities in the project and their expected durations are shown in the following precedence network:

image text in transcribed
Crashing costs for each activity are:
image text in transcribed
a. Determine the minimum-cost crashing plan that will take off six weeks from the project duration.
b. Plot the total cost curve against project duration. What is the optimum number of weeks to crash the project?
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 978-0071091428

4th Canadian edition

Authors: William J Stevenson, Mehran Hojati

Question Posted: