A construction project has indirect costs totalling $40,000 per week Major activities in the project and their
Question:
A construction project has indirect costs totalling $40,000 per week Major activities in the project and their expected durations are shown in the following precedence network:
a. Determine the minimum-cost crashing plan that will take off six weeks from the project duration.
b. Plot the total cost curve against project duration. What is the optimum number of weeks to crash the project?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Operations Management
ISBN: 978-0071091428
4th Canadian edition
Authors: William J Stevenson, Mehran Hojati
Question Posted: