A furniture maker has received an order for 100 units of its kitchen table to be delivered
Question:
Monday to Friday. Currently, the company has 20 units of lumber in stock, and purchase lead time for lumber is one work day.
a. Calculate the manufacturing lead time for each operation and draw the product structure tree.
b. Perform material requirements planning for this order. What action should be taken now?
c. How would your answer for lumber change
i. If the safety stock for lumber is 20 units?
ii. If lumber is purchased in batch size of 250 units?
iii. If 250 units are scheduled to be received on March 13?