A local tool and die shop has the following jobs to be processed. Today is day 120:

Question:

A local tool and die shop has the following jobs to be processed. Today is day 120:

Date Job Arrived Processing Days Required 25 30 Job Due Date Job 100 130 140 90 40 170 95 120 50 170 110 20 180


Using the critical ratio rule, determine the sequence in which the jobs should be processed.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Managing Global Supply Chains

ISBN: 978-1506302935

1st edition

Authors: Ray R. Venkataraman, Jeffrey K. Pinto

Question Posted: