A manufacturer of sails for small boats has a group of custom sails awaiting the last two

Question:

A manufacturer of sails for small boats has a group of custom sails awaiting the last two processing operations before the sails are sent to the customers. Operation 1 must be performed before operation 2, and the jobs have different time requirements for each operation. The hours required are as follows:JOB 8 9 1 2 3 4 5 10 Operation 1 5 3 4 4 Operation 2 8 3 8 2 4 2. CO CO CO

a. Use Johnson’s rule to determine the optimal schedule.
b. Draw a Gantt chart for each operation.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Processes and Supply Chains

ISBN: 978-0134741062

12th edition

Authors: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman

Question Posted: