A Northern British Columbia lumberyard has four jobs on order, as shown in the following table. Today

Question:

A Northern British Columbia lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard€™s schedule.

Job Due Date Remaining Time (days) A. 212 B 209 3 208 D 210


In what sequence would the jobs be ranked according to the following decision rules:
a) FCFS
b) SPT
c) LPT
d) EDD
e) Critical ratio
Which is best and why? Which has the minimum lateness?