A service center has the planned and actual inputs and outputs (in standard hours of work) shown in the following table. Given a beginning backlog of 13 standard hours of work, compute the actual backlog of work each day:

3 Day Planned input Actual input 5' 30 28 30 25 30 25 32 31 26 Planned output 30 27 30 30 30 Actual output 30 28 29 30 2